| Modul | Deskripsi | Kelompok | Tanggal | Durasi | PM | Fullstack | QA | Status | PRD | Prototype | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. RBAC | — | A-1 (SIAKAD) | 29 Jun – 24 Jul | 2 sprint 1 bulan | Muna | BasithAhsanIntan | Intan | Todo | — | — | |
| 2. Login | — | A-1 (SIAKAD) | 27 Jul – 14 Agu | 1.5 sprint 3 minggu | Muna | BasithAhsanIntan | Intan | Todo | — | — | |
| 3. Setup Kelas | — | A-1 (SIAKAD) | 17 Agu – 4 Sep | 1.5 sprint 3 minggu | Muna | BasithAhsanFira | Fira | Todo | — | — | |
| 4. (Manajemen) Perwalian dan KRS | — | A-1 (SIAKAD) | 7 Sep – 2 Okt | 2 sprint 1 bulan | Muna | BasithAhsanFira | Fira | Todo | — | — | |
| 5. (Dosen) Perwalian dan KRS | — | A-1 (SIAKAD) | 5 Okt – 30 Okt | 2 sprint 1 bulan | Muna | BasithAhsanFira | Fira | Todo | — | — | |
| 1. (add) Import Inventaris | — | A-2 (SIAKAD) | 29 Jun – 3 Jul | 0.5 sprint 1 minggu | Muna | AdamAhsan | Fira | Todo | — | — | |
| 2. Pengaturan Kurikulum | — | A-2 (SIAKAD) | 6 Jul – 24 Jul | 1.5 sprint 3 minggu | Muna | LampungUntaraFira | Fira | Todo | — | — | |
| 2. Pengaturan Akademik | — | A-2 (SIAKAD) | 27 Jul – 14 Agu | 1.5 sprint 3 minggu | Muna | LampungUntaraIntan | Intan | Todo | — | — | |
| 3. Data Mahasiswa | — | A-2 (SIAKAD) | 17 Agu – 4 Sep | 1.5 sprint 3 minggu | Muna | LampungUntaraIntan | Intan | Todo | — | — | |
| 4. Infrastruktur APPS Mahasiswa | — | A-2 (SIAKAD) | 7 Sep – 25 Sep | 1.5 sprint 3 minggu | Muna | AfinLampungUntaraFira | Fira | Todo | — | — | |
| 5. (Mahasiswa) Perwalian dan KRS | — | A-2 (SIAKAD) | 28 Sep – 23 Okt | 2 sprint 1 bulan | Muna | AfinLampungUntaraFira | Fira | Todo | — | — | |
| 1. Beranda, Jalur, Prodi | — | B-1 (PMB) | 29 Jun – 10 Jul | 1 sprint 2 minggu | Muna | AdamDimasIntan | Intan | Todo | — | — | |
| 3. CMS | — | B-1 (PMB) | 13 Jul – 24 Jul | 1 sprint 2 minggu | — | BasithAhsanIntan | — | Todo | — | — | |
| 4. Manajemen Jalur | — | B-1 (PMB) | 27 Jul – 7 Agu | 1 sprint 2 minggu | Muna | AdamDimasIntan | Intan | Todo | — | — | |
| 5. Pendaftaran dan Pembayaran | — | B-1 (PMB) | 10 Agu – 28 Agu | 1.5 sprint 3 minggu | Muna | AdamDimasIntan | Intan | Todo | — | — | |
| 5. Seleksi Fase 1 | — | B-1 (PMB) | 31 Agu – 18 Sep | 1.5 sprint 3 minggu | Muna | AdamDimasIntan | Intan | Todo | — | — | |
| 6. Seleksi Fase 2 | — | B-1 (PMB) | 21 Sep – 9 Okt | 1.5 sprint 3 minggu | Muna | AdamDimasIntan | Intan | Todo | — | — | |
| 1. Pengajuan Anggaran Dekstop | — | C-1 (Operasional Strategis) | 15 Jun – 10 Jul | 2 sprint 1 bulan | Putri | HumamDhistaMardiyah | Mardiyah | Todo | — | — | |
| 2. Sistem Akreditasi | — | C-1 (Operasional Strategis) | 13 Jul – 4 Sep | 4 sprint 2 bulan | Putri | HumamAriIkhwanDhistaMardiyah | Mardiyah | Todo | — | — | |
| 3. Website Direktorat | — | C-2 (Website) | 22 Jun – 3 Jul | 1 sprint 2 minggu | Muna | AriIkhwanMardiyah | Mardiya | Todo | — | — | |
| 3. CMS Website Direktorat | — | C-2 (Website) | 6 Jul – 17 Jul | 1 sprint 2 minggu | Muna | AriIkhwanMardiyah | Mardiyah | Todo | — | — |